|
April 1998
Active Mining in Butte and
the Berkeley Pit
PitWatch Issue Volume 3,
Number 1
We can explain some, but not
all, aspects of the relationship between the Berkeley Pit and
Montana Resources (MR), the corporation actively mining here
in Butte. As you may recall, last year MR and ARCO hammered out
an agreement on Berkeley Pit clean-up responsibilities, but the
details were not made public. Here's what we do know:
The Present
Horseshoe Bend. For the past
two years, MR and ARCO have been diverting and treating the stream
of water that once flowed directly into the Berkeley Pit from
the northeast. The Horseshoe Bend diversion project has reduced
by about half the amount of water entering the Pit. MR reuses
this water in its concentrating operations. MR and ARCO share
the project's annual operating cost of about $2 million. Around
$1.6 million of that goes toward buying and transporting lime,
which is used to treat the water.
Continental Pit Dewatering. From March through October, MR pumps
groundwater out of the south end of the Continental Pit to keep
the area dry for future mining. Starting this summer, the company
may begin pumping additional water out of the north end of the
pit, with all water routed to the MR concentrator. This pumping
diverts water that could otherwise flow into the Berkeley Pit
from the east.
The Future
Monitoring Program Expansion.
Over time, the monitoring well system will be expanded south
and east to cover the entire Berkeley Pit/Continental Pit Complex,
rather than just the area around the Berkeley Pit. This expansion
will be necessary because groundwater pumping at the Continental
Pit will eventually take place at an elevation lower than the
water level of the Berkeley Pit. Pumping now occurs about 90
feet above the Berkeley Pit water level, but over the next 20
years, MR plans to expand the Continental Pit eastward and southward
and mine it down to 4,986 feet166 feet below the current
Berkeley Pit water level (all USGS elevations).
When this new low spot is created,
some water that would otherwise flow west toward the Berkeley
may instead start flowing east toward the Continental. Water
levels in the monitoring wells between the two pits (such as
Well H) will be affected by this change, although exactly how
they will react is unknown. Most importantly, however, all water
will still be confined to the mining area with flow going toward
the two pits.
Central Zone Mining. MR may
also expand active mining westward into the Central Zone area
between the two pits. Five bedrock monitoring wells (H, C, D1,
D2, and DDH-2) lie within this zone and would be mined out. The
Continental Fault, which runs along the Continental Pit's current
west border, would also be mined out, eliminating what is now
a partial groundwater barrier between the two pits. MR officials
said the Central Zone is rich in copper, but they also admitted
that a great deal of research must be done to determine the feasibility
of mining there.
October 1998
High
Water History
PitWatch Issue Volume 3,
Number 2
When the Anaconda Company stopped
pumping groundwater out of the West Camp in 1965, the water level
in the Travona quickly climbed to over 5,500 feet. Water started
seeping into basements in the area bounded by Iron Street in
the north, Front Street in the south, Montana Street in the west,
and Maryland Street in the east. Surface water seeps were also
observed north of Centennial Avenue between Montana Street and
Missoula Gulch. In response, what became known as "Relief
Well No. 21" was installed close to the spot where todays
new main pump is located. Keeping the Travona water more than
70 feet lower than it was back in 1965 should ensure that this
case of high water history wont repeat itself.
Learning
About The Westcamp
PitWatch Issue Volume 3,
Number 2
Previous issues of PitWatch
have been devoted almost exclusively to the Berkeley Pit and
surrounding "East Camp" underground wells and mine
workings. Another area of the underground water system called
West Camp also deserves our attention.
The West Camp lies southwest of the Berkeley Pit/East Camp drainage
and includes the Travona, Emma, and Ophir mine workings. Like
in the East Camp, the groundwater in this area has been closely
monitored since 1982 to make sure the water does not rise above
a certain levelin this case 5,435 feet. Since November
1989, pumping operations have kept the water below this level.
In the late 1950s, the West Camp mine workings were sealed off
from the rest of the shafts and drifts on the Butte Hill by a
series of barriers, or bulkheadssome made of wood, some
cement. Three main cement bulkheads block the connections between
the Emma and Original mines at the 1,600-foot level and the Emma
and Colorado mines at the 1,400- and 1,000-foot levels.
Anaconda Company crews installed the bulkheads for two main reasons:
1) they were finished mining in the West Camp and 2) they wanted
to increase the efficiency of continued operations in the other
mines and the Berkeley Pit. The bulkheads allowed them to eventually
reduce both the volume of groundwater pumped and the area underground
that required fresh air. However, even after the bulkheads were
installed, they continued to pump water out of the Emma shaft
until 1965.
Over the years, leakage has occurred through the bulkheads, but
according to monitoring data, it appears that the West Camp water
system remains mostly independent. The groundwater levels in
its shafts are several hundred feet higher than those in the
other mine workings, indicating that the bulkheads still separate
the two areas.
After studying the West Camp in the late 1980s, the U.S. Environmental
Protection Agency (EPA) ruled that the water in the Travona shaft
could rise to an elevation of 5,435 feet without threatening
human health or the environment. However, if the water were to
rise above this level, EPA believes it could eventually flow
untreated into Silver Bow Creek, and ARCO would face daily fines
starting at $5,000 and increasing to $10,000 after 10 days.
To ensure that the West Camp water stays below 5,435, groundwater
is pumped from the Travona shaft into a county sewer line and
on to the Metro Sewer plant. ARCO pays Butte-Silver Bow about
$30,000 a month to treat this water, depending on the volume
received. Treatment mainly involves reducing the water's arsenic
content.
Recently, ARCO installed a larger main pump south of the Travona
near Centennial Avenue. It can handle 100 more gallons per minute
than the current pump (330 compared to 230), and it should go
on line sometime this fall. The Travona pump will then become
the back-up, used only when needed.
The old pump is due for some downtime, as it has been working
at near full capacity for more than a year to keep up with rising
water. For example, in September 1997, the Travona water hit
5,432 feetjust 3 feet below the critical mark. The current
level, last measured on September 30, is 5,422 feet.
Bureau of
Mines Publishes 15-year Report on Mine Flooding
PitWatch Issue Volume 3,
Number 2
The Montana Bureau of Mines
and Geology has issued a 15-year report containing water-level
data collected from all of the mine flooding monitoring points
from 1982 to 1997. The comprehensive document also includes numerous
graphs, maps, and historic photographs, plus explanations of
the various areas that comprise the Butte Mine Flooding Superfund
Site. To request a copy, call 496-4167. In 1999, the Bureau will
release a companion report on water quality in these monitoring
wells and shafts. Both reports will be updated annually. |