INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 1, Number 1 (April 1996)

Q:

What is the Critical Water Level?

A:

The official "Record of Decision" (called a "ROD"), issued in September 1994 by the U.S. EPA and Montana Department of Environmental Quality (MDEQ), established the critical water level at 5,410 feet.

According to the agencies, the 5,410' level includes a safety buffer of at least 50 feet and represents the point at which the Pit water could potentially seep into Silver Bow Creek or into the alluvial groundwater aquifer that supplies some local wells.

The ROD stipulates that the parties responsible for treating the Pit water—ARCO and Montana Resources—must begin pumping and treating the Pit water before the water reaches this critical level. If they don't, they will be fined $25,000 per day.

Back to top

Q:

Does this Critical Water Level apply only to the Pit?

A:

No. Pumping and treating of Pit water must begin when the 5,410-foot level is reached at ANY of the water-level monitoring sites on the Hill, in what's called the "East Camp." These sites include the Anselmo, Granite Mountain, Kelley, Belmont, and Steward mine shafts, as well as several other monitoring wells established to the south and the east of the Pit.

Presently, the water level at these sites is now 20-40 feet higher than the level in the Pit. So, the 5410-foot level should be reached sooner at these sites than in the Pit, which means water pumping and treating would begin that much sooner.

Back to top

Q:

When will the Critical Water Level be reached?

A:

It's impossible to predict exactly when the water will reach the 5,410-foot mark. Today, we know the water level in the Pit is 284 feet below the 5,410-foot mark, and it is expected to take about 25 years, until the year 2021, for the water to reach that critical level.

But over time, things can happen that may affect the prediction. For example, in 1995, more water flowed into the Pit than was expected, presumably due to higher than normal rainfall.

Over the next two decades, we have to keep a close watch on the actual data from the monitoring sites. If the measurements prove to be different from the predictions, the timeline to build the treatment plant will have to be adjusted accordingly.

Back to top

Q:

How does the Horseshoe Bend pumping project affect the water level in the Pit?

A:

Now that the Horseshoe Bend pumping station is on line, the amount of water entering the Pit has been cut in half. So, the rate at which the water level will rise should slow down considerably.

Before the diversion project, 3 million gallons of water flowed into the Pit from underground aquifers and another 3 million gallons of surface water flowed in via the Horseshoe Bend "waterfall," which was visible from the Pit viewing stand. On April 15, 1996 ARCO and Montana Resources started diverting this surface water into Montana Resources' tailings ponds.

This action is the first of many that were ordered by the EPA and the MDEQ as part of the ROD concerning the Pit Superfund project. The next PitWatch will discuss the Horseshoe Bend diversion project in detail.

Back to top

Q:

Why wait until the water reaches the 5,410-foot level before starting the pumping and final treatment?

A:

The main reasons to postpone the construction of a treatment plant is to allow time for new treatment technologies to be perfected and to reduce the generation of acid mine drainage as much as possible.

Right now, the only feasible and proven water treatment method is hydroxide precipitation, which cleans the water but also creates a big disposal problem—about 500 to 1000 tons per day of heavy metal sludge.

A handful of technologies that could both clean the Pit water and recover the valuable metals are in the development stages. The theory is that when it becomes absolutely necessary to begin pumping and treating the water, perhaps one or a combination of these new technologies will be ready to be applied to such a large-scale project.

The ROD calls for a reevaluation of treatment technologies to take place when the water level reaches 5,260 feet, which is projected to be around 2008. PitWatch will devote a future edition to potential treatment technologies.

Back to top