INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 2, Number 1 (April 1997)

Q:

Are the water levels in the Pit and the monitoring sites rising as expected?

A:

Yes. Even with heavy snowfall this winter, the Pit's level continued to rise as expected. In general, nothing out of the ordinary is happening. The water levels in the monitoring wells are also rising as predicted and continue to be 10 to 20 feet higher than the Pit's water level. These higher measurements indicate that the surrounding ground water is still flowing inward, toward the Pit, much like runoff flows down into storm drains.

In our monthly column in August 1996, we mentioned that the water levels at Monitoring Site DDH-5 east of the Pit were rising and falling, rather than steadily rising. From September on, however, the water has risen steadily at least one foot per month. We checked into the erratic readings and found out that the problem was unrelated to the water in the well. As it turns out, the monitoring equipment was accidentally bumped which led to the incorrect summer measurements. In September, the well casing was removed and then replaced.

Back to top

Q:

Is the Horseshoe Bend diversion project working as planned?

A:

Yes. Since the diversion project went on-line last April, only about half as much water is entering the Pit - about 3 million gallons per day instead of 6 million. This means that the water level now rises about one foot per month instead of two feet. The diversion project is part of the cleanup efforts ordered in the September 1994 Record of Decision (ROD) by the U.S. EPA and the Montana Department of Environmental Quality (MDEQ).

The cost of this water diversion and treatment project included about $400,000 in start-up costs and now $1-$2 million in annual operating expenses. These costs are shared by ARCO and Montana Resources.

Here's how the diversion project works: The stream of water that used to flow into the Pit's northeast side is now pumped uphill to the Yankee Doodle tailings pond. Before its release into the pond, the highly acidic water is mixed with a combination of lime and tailings that is pumped up from the Montana Resources' concentrator. This mixing process draws some of the metals away from the water and reduces its acid content, leaving it clean enough to be reused. Each day, about 22 million gallons of water from the tailings pond are piped down to the concentrator for reuse. This amount of water includes not only Horseshoe Bend flow, but also water that separates out from the Continental Pit tailings.

Back to top

Q:

How long will it be before the water in the Berkeley Pit is treated?

A:

With the Horseshoe Bend project now in place, water treatment has begun. As for the water in the Berkeley Pit, treatment will begin as soon as the water level in the Pit or in any of the surrounding monitoring wells reaches 5,410 feet—the level determined to be the "critical water level" by EPA and MDEQ. That level is expected to be reached around 2021. To ensure that Pit water treatment starts when it's needed to protect human health and the environment, the plant will be ready to go four years beforehand.

Back to top