INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 4, Number 2 (October 1999)

Q:

Where is the water coming from?

A:

The water is naturally occurring groundwater. It started flowing back into the area in 1982 when the central pump station in the Kelley Mine was turned off. For nearly a century before 1982, groundwater under the Butte Hill had been constantly pumped to the surface to allow for mining.

This pumping created a vast cone-shaped area underground that was kept unnaturally dry. The bottom of the Berkeley Pit lay near the bottom of this dry area. When the pumping stopped, the Pit started working like a big sink, drawing water toward it from all directions.

Back to top

Q:

Why is the water polluted?

A:

The water in the Berkeley Pit is a good example of acid mine drainage, which is mainly caused by the high sulfur content in the rock in the Butte Hill. The sulfur reacts with air and water to become sulfuric acid. As this acidic water flows through the underground mine workings and rock fractures, it eats away at the metals in the rocks and dissolves them into the water.

Back to top

Q:

When will the water be pumped and treated?

A:

Some pumping and treating is underway. In April 1996, water flow into the Pit was reduced by about half when a surface stream called Horseshoe Bend started being diverted. Horseshoe Bend water is treated with lime and pumped up to Montana Resources' (MR's) tailings pond north of the Pit. From there, some of the water is piped down to MR's concentrator for reuse. To date, more than 6 billion gallons of Horseshoe Bend water have been kept out of the Pit.

As for the water in the Pit, pumping and treating must start before the Pit water level - OR the water level in surrounding mine shafts and monitoring wells - approaches 5,410 feet above sea level. If present trends continue, the water will approach that elevation around 2021.

Back to top

Q:

What assurances are there that a treatment plant will be ready to go when it’s needed?

A:

Design for the treatment plant must begin eight years before the water is due to approach 5,410, and the plant must be ready to go four years before it's needed. Based on current water flows and monitoring data, plant design should start around 2013, with plant completion around 2017.

But each year, water level changes are reviewed and the timeline is adjusted accordingly. Updating the timeline is part of the official Record of Decision (ROD) that spells out the treatment requirements. This decision was issued in September 1994 by the U.S. Environmental Protection Agency (EPA) and the Montana Department of Environmental Quality (MDEQ).

Back to top

Q:

How will the water be treated?

A:

That decision is not yet final. Right now, the only proven, cost-effective treatment method is adding lime. Lime would clean the water by reducing its acid content and pulling out the metals. But this process would generate 500 to 1,000 tons per day of heavy metal sludge, creating a huge waste disposal problem.

Several other water treatment technologies are under development. It is hoped that by the time plant design must start, one or a combination of new treatment methods will be proven effective on a large scale.

Back to top

Q:

Why postpone additional treatment until the water approaches 5,410-foot elevation?

A:

After years of study, EPA and MDEQ determined that the water does not pose a threat to human health or the environment as long as it is kept below the 5,410-foot level. Officials are confident that the contaminated water in the underground workings will continue to flow toward the Pit and stay there.

Potential advantages to postponing treatment include the following: 1) It reduces project costs for operation and maintenance of a treatment plant; 2) It allows time for new treatment technologies to be perfected, and 3) It may lead to improved water quality. Some scientists believe that letting the water rise to maximum safe levels will eventually lower its acid and metals content by reducing the amount of sulfur-bearing rock that’s exposed to air.

Back to top

Q:

What would happen if the water were to rise above 5,410?

A:

Above 5,410, the water would not flood Butte by coming up over the rim of the Pit onto Continental Drive. The rim's elevation, at its lowest point, is about 5,510, some 100 feet higher. But above 5,410scientists believe at about the 5,460-foot levelthe water could begin to flow away from the Pit into the cracks and crevices of the groundwater system below the surface, potentially harming the water quality of local wells and Silver Bow Creek.

Back to top

Q:

Who is responsible for treating the water?

A:

The Atlantic Richfield Co. (ARCO), which bought out the Anaconda Co. in 1977, and Montana Resources (MR), the company now mining in the Continental Pit adjacent to the Berkeley, are responsible, along with four other entities affiliated with MR–Asarco, Inc.; AR Montana Corp.; MR Inc., and Dennis Washington. If they fail to pump and treat the water to keep water levels below 5,410 feet, the U.S. government (EPA) can take over the project and charge these companies up to three times the project cost.

Back to top

Q:

What's happening in the meantime?

A:

The entire mine-flooding system is being monitored to track water movement and water quality. Water levels are measured every month in the Pit and in 13 mine shafts and 58 monitoring wells. Water quality is analyzed twice a year.

The monitoring program keeps tabs not only on the East Camp groundwater system centered around the Pit, but also on water movement in the West and Outer camps, generally west of the Pit. If the monitoring data reveal that water levels are rising faster than expected, the responsible companies will be required to take the necessary actions sooner than planned.

Back to top