INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 5, Number 2 (October 2000)

Q:

Is the water level in the Pit rising according to predictions?

A:

No. The suspension of mining in July 2000 has disrupted the predictions since more water is entering the Berkeley Pit than was expected (see photos at right). The extra water, about four to five million gallons a day, is coming from the Horseshoe Bend flow, which had been diverted away from the Berkeley Pit since April 1996. That diversion project became part of mine operations. So, until Montana Resources starts mining again, or figures out another way to divert and treat the Horseshoe Bend flow, the water level in the Berkeley will be rising twice as fast as expected.

Back to top

Q:

Why is the water in the Pit allowed to rise higher and higher? Why wait to build a treatment plant?

A:

Pitwatch readers have asked these questions repeatedly. It's hard for residents to understand why something isn't being done right away to deal with the toxic water in the Pit. For the parties responsible for the problem and for any adverse impacts from the water, the reasons for waiting are a combination of science, time and money.

In general, the Berkeley Pit is considered a big holding tank, with a well-defined capacity. Based on years of scientific study, the EPA and MDEQ have determined that the water in the Pit does not and will not pose a threat to human health or the environment as long as the level stays below the 5,410-foot level. This conclusion is part of the Record of Decision that dictates when and what happens at the Pit. With the current level at 5,189, there is about 220 feet of "storage space" left in the Pit. As owners responsible for water treatment, Montana Resources and ARCO are trying to use that "storage space" in the most effective way.

For starters, any delay reduces costs to operate and maintain a treatment facility. Annual costs are expected to exceed $3 million, so for as long as possible, it is considerably cheaper to manage the Pit as storage space. Also, some scientists believe that letting the water rise to maximum safe levels will eventually lower the water's acid and metals content by reducing the amount of sulfur-bearing rock that's exposed to air. That may improve water quality and make it cheaper to treat the water when the time comes.

In addition, the delay allows time for new treatment technologies to be perfected. If water treatment were to begin today, the most cost-effective, reliable technology would be lime precipitation, which is essentially mixing the toxic water with lime. But this process would produce massive amounts of toxic sludge, which creates another waste disposal problem in Butte. On the other hand, with the benefit of time, the hope is that innovative, cost-effective technologies will emerge to recover valuable metals in the water, or at the very least, reduce the amount of toxic sludge produced.

For now, the emphasis is to monitor the water carefully. As storage space in the Pit begins to run out, safeguards are in place to make sure a treatment plant will be ready. As shown on the timeline (see bottom of pages 2&3), design work must begin eight years before the water in any of the wells or shafts is expected to reach the 5,410' elevation and the treatment plant must be ready to operate four years ahead of time. This timeline is reviewed and evaluated by the Agencies every year and updated as needed.

Back to top