INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 6, Number 1 (April 2001)

Q:

Is the water level in the Pit rising according to predictions?

A:

No. Due to the suspension of mining in July 2000, more water has been entering the Berkeley Pit in the past nine months than was expected. The extra water (about three to four million gallons a day) is coming from the Horseshoe Bend flow, which had been diverted away from the Berkeley Pit since April 1996 as part of mine operations.  Until Montana Resources starts mining again, or a facility is built to treat the Horseshoe Bend flow, the water level in the Berkeley will be rising twice as fast as originally predicted. 

Back to top


Q:

If more water than expected is flowing into the Berkeley Pit, will the Critical Water Level be reached sooner?

A:

Yes.  Montana Resources and ARCO have recently updated the computer model used to estimate the timeline for reaching the Critical Water Level of 5,410’ above sea level.  The updated prediction now estimates the water level in the Anselmo shaft (the highest monitoring point in the system) should reach 5,410’ in about 2018, about three years sooner than was predicted in 1999.

The new target date is based on two important assumptions: 1) that mining is permanently suspended, and 2) that treatment of Horseshoe Bend water will not start until July 2003. But regardless of the mine's future or when water treatment begins, the model will be updated every year, with a full accounting of the amount of Horseshoe Bend water that goes into the Pit, and the timeline will be revised accordingly.

Back to top

Q:

How does the revised date to reach the Critical Water Level affect the long-term plan to treat Berkeley Pit water?

A:

Given the updated prediction that the Critical Water Level will be reached sooner, EPA has required Montana Resources and ARCO to revise the timeline to select, design, build and operate a facility for treating Berkeley Pit water. All milestones have been pushed forward by three years. For example, the design for the water treatment facility must be initiated during 2010, and the facility must be completed and operational by 2014.

In addition, as required under the Record of Decision, the companies were expected to re-evaluate appropriate water treatment technologies when the water level in the Pit reached the 5260’ elevation. That level was expected to be reached in 2007, but now, the new prediction is late-2004. As a result, the decision to select a treatment method will also be made three years sooner.

Back to top

Q:

Who would be responsible for water treatment if the mine closes permanently?

A:

Under a clear EPA order, both Montana Resources and ARCO are responsible for treating Berkeley Pit water. Under the Superfund law, if one company is unable to pay its share, the other company must pay all the costs of cleanup. The company paying the full cleanup costs would likely take some legal actions to recover a fair share of those costs from the other company.

Back to top