INFO@PITWATCH.ORG  

ARE YOU A TEACHER?
CURRENT WATER LEVEL: 5,239.47 ft.

COMMON
QUESTIONS &
ANSWERS

PITWATCH ISSUES:
FALL 2003

SPRING 2003

FALL 2002
SPRING 2002
FALL 2001
April 2001
October 2000
April 2000
October 1999
April 1999
October 1998
April 1998
October 1997
April 1997
April 1996

Volume 6, Number 2 (FALL 2001)

Q:

Is the water level in the Pit rising according to predictions made in 1994?

A:

No. Since Montana Resources suspended mining June 30, 2000, more water has been entering the Berkeley Pit than expected. The extra water - less than 3 million gallons a day - is coming from the Horseshoe Bend flow, which had been diverted (since 1996) from the Berkeley Pit under an EPA order to reduce the rate of rise. Until a facility is built to treat the Horseshoe Bend flow, the water level in the Berkeley will be rising faster than was originally predicted in 1994.

Back to top

Q:

How much faster is the water level in the Pit rising since mining was suspended?

A:

In the fifteen months prior to June 30, 2000, the water level in the Pit climbed about 14 feet, or about one foot per month. During the fifteen months since the mine closed until September 30, 2001, the water level in the Pit has gone up almost 26 feet, or about 1.5 feet per month.

Back to top

Q:

If more water than expected is flowing into the Berkeley Pit, will the Critical Water Level be reached sooner?

A:

Yes. Every year, ARCO and Montana Resources update the computer model used to estimate the timeline for reaching the Critical Water Level of 5,410' above sea level. The most recent update now predicts the water level in the Anselmo shaft (the highest monitoring point in the system) should reach 5,410' in about 2018, about three years sooner than originally expected. That means design work for a facility to treat Berkeley Pit water will have to start as early as 2010, with construction complete by 2014.

The new target dates are based on two important assumptions: 1) that mining does not start again before 2018, and 2) that treatment of Horseshoe Bend water will start in July 2003. If these two things don't happen, the timeline to reach the Critical Water Level will be revised again.
Back to top

Q:

If a facility is built by 2003 to treat Horseshoe Bend water, could the same plant eventually be used to treat Berkeley Pit water?

A:

Yes. If the mine doesn't re-open, the Horseshoe Bend water treatment plant will have to be built and operating by 2003 (see back page). In their current plans, ARCO and Montana Resources have indicated that this same facility will have the capacity to also treat the water from the Berkeley Pit - starting in 2018 or whenever the water in the monitoring wells approaches the Critical Water Level of 5,410'.

Back to top

Q:

Is there a difference between the water quality of the Berkeley Pit water and the Horseshoe Bend water?

A:

Yes, the chemistry of the Berkeley Pit and the Horseshoe Bend water is different. Recent measurements showed the Horseshoe Bend water has a pH ~3.2, has a copper content of 70 ppm (parts per million), and has Total Dissolved Solids ~6500 ppm.

By contrast, the Berkeley Pit water is more acidic, with a pH ~2.6, has more than twice as much copper, 170 ppm, and has twice as many dissolved minerals, with Total Dissolved Solids ~12,000 ppm.

Back to top